Implementation – Managing PPPs
18.4 Renegotiation
The public-private partnership process does not end when the private
partner is chosen and all the relevant papers are signed. It
is not possible for a contract to handle all the uncertainties
that the future holds. Thus, careful provision must be made to
deal with unexpected events over the life of the contract.
For short-term contracts, renegotiation would seem to be unnecessary
provided adequate and automatic safeguard procedures for
changes in conditions have been built into the contract. However,
in the real world governments change and the new people in
power may be dissatisfied with the initial contract terms. Thus,
it is prudent to specify renegotiation procedures clearly and to
allow independent arbitration if necessary.
In addition, the contract could require amendments if the
legitimate needs of the users of the service are not satisfied
within the agreed boundaries of the contract.
Even more critical, however, is the presence of a renegotiation
statement in the medium- and long-term contracts that constitute
the majority of PPP projects. The poorer the quality of
information from the start, and the greater the doubts
of both parties about their relationship, the better will be
the chance that renegotiations will have to occur. Therefore, it
is important to introduce clear provisions for renegotiation
and to supplement competition at the bidding stage with future
competitive pressures.
However, before there is a need for a contract renegotiation,
it would be wise to try resolving some of the problems
within the present contract terms and conditions. If this
does not appear feasible/possible, a PPP
Review Panel could
be established. This is an independent body that all parties
would respect, which could be consulted to resolve issues.
The panel would be consulted before resorting to arbitration
or other legal measures that could take years to decide,
during which time the PPP would almost certainly fail [see
Tool 19].
Elements of the contract on renegotiation
The service provider and the municipality should have the right
to renegotiate and the ability to do so if special circumstances
arise, such as if revenues are substantially off target (either
too low to cover costs, or too high and generating too much
profit), or if a structural problem (such as a problem with
the underground water supply) is discovered by the provider,
which was not considered in the original bid. In such cases, both
the public and private parties should follow the mechanisms
to request renegotiation and to renegotiate and settle the issue
as described in the contract.
Renegotiation should be covered as part of the contractual
arrangements, with clear statements about the following:
- The conditions under which adjustment of terms or renegotiation
may occur.
- Who can request renegotiation of the contract?
- How often can renegotiation occur?
- What extensions to the contract – such as adding treatment
works or a new service district – allow or require re-tendering
the contract?
- What is the process by which renegotiation must be initiated
and conducted?
- What are the procedures to be followed, and the organisations
or individuals to be appealed to in the event that the
parties to the contract cannot agree on how to resolve an issue (arbitration
provisions).
In most cases where problems have arisen in PPP
arrangements in the past, contractual difficulties
have been worked out through adjustment or renegotiation
of key contract terms. Such renegotiation requires
good faith on the part of both the government and the
private operator. Where a good working relationship
and collaborative spirit are lacking, on the other
hand, or where political motivations prevent governments
from negotiating, contract termination is the result
of such problems.
Termination of the contract is not beneficial to either
of the parties, unless the new, renegotiated
terms were entirely unacceptable. First and foremost, termination
means that the process has to start again from
the very beginning; the additional effort required to build
new relationships and conduct new negotiations also
brings with it additional transaction costs. Thus provision
for renegotiation is vital for the implementation of a successful
PPP.
In order to prevent and mitigate conflicts and subsequent
contract termination, conflict resolution skills
should be included in the capacity development trainings [Tools
20, 21].


